Measure E Bond

In November 2018, Orinda voters approved a facility bond, Measure E, in the amount of $50,000,000 to update science, technology, engineering, art, and math classrooms; maintain libraries; upgrade technology infrastructure, construct, acquire, and repair classrooms. 
 
Projects funded by Measure E are:
  • Sleepy Hollow NEW Multi-Purpose Room
  • OIS NEW Student Services Building
  • Modernization - ALL schools
    • Windows
    • Insulation
 

Measure I Bond

In November 2018, Orinda voters approved a facility bond, Measure I, in the amount of $55,000,000 to upgrade classroom air conditioning, electrical, fire safety, security lighting, communications, camera systems, classrooms locks; update science, technology, engineering, art, math classrooms; construct, acquire, repair classrooms and facilities. 
 
Projects funded by Measure I include:
  • Heating and Airconditioning (HVAC) Installation - All School Sites
  • Electrical upgrades - All School Sites
  • Network and public announcement (PA)/Clock system - All Schools Sites
  • Modernization - All School Sites
    • Accessibility upgrades
    • Painting
    • OIS 30s Wing Remodel
 

Measure E Projects

Measure E Projects


Measure I Projects

Measure I Projects

Sleepy Hollow Multi Purpose Room Project

Sleepy Hollow Multi Purpose Room Project

Project Status: Completed
Project Description: Demolition of old MPR, construction of new MPR building, construction of ADA accessible elevator, new water lines, new location of BASC buildings, relocation of two portable classrooms, expansion of the parking lot
OIS Student Services Building

OIS Student Services Building

Project Status: Completed
Project Description: Demolition of old classrooms, construction of a new building, relocation of counseling and administrative offices from the 30's wing, and addition of a Wellness Center, ADA accessible walkway and ramps, and covered pathways. 

HVAC Installation

HVAC Installation

Project Status: Completed
Project Description: Installation of Heating, Ventilation, and Air Conditioning (HVAC) units in all instructional spaces in all schools. Districtwide mechanical and electrical upgrades were conducted to support the new HVAC units. 
Districtwide modernization

Districtwide modernization

Project Status: In Construction (Fall 2026)
Project Description: Replacement of all single pane windows with dual pane windows, replacement of all wooden and old doors with metal doors, PA/Clock system upgrade in all classrooms and school spaces, installation of security cameras, insulation in classrooms, removal of old heating equipment and closets, painting of schools. 
Modernization

Modernization

picture of window replacements
picture of insulation replacement
picture of accessibility upgrades